Monday, November 8, 2010

Required IRs 8-Nov-2010

Required IRs up to the shown level

Location Building Backfill Geogride
6-7 (2nd)

8.3
13-14 (1st)

7.9

21`-21``(1st)

8.3

7``-8(2nd)
8.3
8.3

24-25(1st)
13.5
12.8

25-27(1st)
13.3
12.6































Required shuttering IR for Key Stone

Required shuttering and casting concrete IR for P5-P6 3rd step
Coordinates and sketch are attached in the message on email
abnaabadawy@gmail.com

Sunday, November 7, 2010

Fwd: Required IRs 7-Nov-2010




Required IRs up to the shown level

Location Building Backfill Geogride
1-2 7.7
7.7
7.1
2-2`
7.7
7.7
7.1
2`-3
7.7
7.7
7.1










































Saturday, November 6, 2010

Required IRs 6-Nov-2010


Required IRs up to the shown level

Location Building Backfill Geogride
7-8 8.7
8.4
8.3
6-7
8.7
8.4
8.1
5-6
8.7
8.4
8.3
4`-5
8.3
8.3
7.7
4-4`
8.3
8.3
7.7
3-4
8.3
8.3
7.7
13-14

7.9

19-20
Shuttering
Casting

6-7 (2nd)
8.3


7``-8 (2nd)
8.3

 
1-2

7.1
 
2-2`

7.1
 
2`-3

7.1
 


Wednesday, November 3, 2010

Key Stone work report 3-Nov-2010

  • Building:-
    • P13-P14 "60 cm" (rest of it)
    • P6-P7` first course
  • Geogride:-
    • P13-P14
    • P21`-P21``
  • Backfill and crushed stone - 30 cm:-
    • P1-P2
    • P2-P2`
    • P2`-P3
    • P3-P4
    • P4-P4`
    • P4`-P5
    • P5-P6
    • P16-P17

Required IRs 3-Nov-2010

Required IRs up to the shown level

Location Building Back fill Geogride
1-2 7.1 7.1  
2-2` 7.1 7.1  
2`-3 7.1 7.1  
3-4   7.7  
4-4`   7.7  
4`-5   7.7  
5-6   8.3  
13-14 7.9 7.3 7.3
15-16   8.2  
16-17   8.2  
17-18   8.5  
18-19   8.5  
21`-21``   8.3  

Tuesday, November 2, 2010

Key Stone work report 2-11-2010

  • Shuttering:-
  1. P19-P20 ( 1/2 distance)

  • Building:-
    1. P13-P14 "60 Cm" ( 1/2 distance )
    2. P7``-P8 1st course

  • Geogride:-

    1. P1-P2
    2. P2-P2`
    3. P2`-P3
    4. P7`-P7``

  • Back fill + Crushed stone ( 30 Cm )


    1. P3-P4
    2. P4-P4`
    3. P4`-P5
    4. P5-P6
    5. P13-P14

  • Crushed stone only ( 30 Cm )

    1. P15-P16